Realization of works and deliveries on the FPF-1 off-shore platform

 

      FPF-1 is an oil rig built in 1977 in the Japanese shipyard MHI Hiroshima Machinery Works. It is approx. 30 meters high, 82 meters long and 75 meters wide. The works were carried out as part of the reconstruction carried out at "Stocznia Remontowa S.A.", in which the rig underwent a thorough reconstruction to a floating refinery.

 

.

Podgrzewacz2.png

The scope of assembly

As part of the commissioned tasks, PBUCH realized on this unit comprehensive system equipment deliveries and assembly of HVAC installations, mainly in the residential part of the platform.
We have made air-conditioning and ventilation installations, refrigeration installations and air receivers.

We provided, equipment of PBUCH production:

  • chillers
  • cold stores equipment
  • hot water module
  • marine air-conditioners,
  • pressure tanks